Permits · Easy
Building permits in New Brunswick: needed everywhere, including rural areas
In short: A building permit is now needed to construct anywhere in New Brunswick. Regional service commissions issue them in rural districts; a few small buildings are exempt.
Before you start: check these
0 of 6 done
Under New Brunswick's Building Code Administration Act, the permit requirement applies province-wide, including rural districts, and the National Building Code adopted by regulation applies to the work.
A permit for construction, demolition and change of use
Section 4(1) says no person shall construct a building in the Province unless a building permit has been issued and the work conforms to the Code, applicable by-law standards and the permit conditions. A demolition permit is needed to demolish (section 4(2)), and a change of use that affects the Code's occupancy classification needs a building permit even if no construction is planned (section 7).
Who issues it
A building inspector issues the permit once the application, development officer approval and fee conditions are met (section 6). Building inspectors include those working for a regional service commission (section 1). The province's regulation covers local governments without a building by-law and rural districts, and fees under it are paid to the regional service commission (sections 22(2) and 22(3)). In a city or town with its own by-law, apply there.
Small buildings that are exempt
General Regulation 2021-2, section 5, exempts from the Act, the regulation and the Code: an accessory building of no more than 55 m² that is not for overnight accommodation; a building used only on a construction site and not for overnight stays; a building of no more than 58.06 m² intended for overnight accommodation; and a temporary building that will not stay more than 28 days. The regulation text should be checked for the exact scope before relying on an exemption, and development or zoning approval can still be needed.
What the application needs
For rural districts and local governments without a building by-law (regulation section 13), section 14(1) lists what a building permit application must include: the fee, names and contact details of the owner and all constructors, designers and inspection agencies, the property location and account number, a detailed description of the work, the approximate cost, the intended use, scaled drawings and specifications, and any special building system, material or appliance.
Inspections and enforcement
At least one inspection is required at completion of footings and foundations before backfill, at substantial completion of framing, and at completion or before occupation (regulation section 9(1)). The owner sends a notice of readiness, and the inspection is to be made within two days or at an agreed time (sections 10(1) and 10(2)). Building without a permit is an offence under section 16(6) of the Act, and inspectors may enter property to check compliance, with limits for occupied parts of a home (sections 9 and 12).
Article done. One mistake you will not repeat. Next failure →
Need a pro for this?
References
- Government of New Brunswick. Building Code Administration Act, S.N.B. 2020, c. 8 (current to January 1, 2024), Web page, ss. 1, 4, 6, 7, 9, 12, 16, 22. Accessed 2026-11-04.
- Government of New Brunswick. General Regulation, N.B. Reg. 2021-2, under the Building Code Administration Act (consolidated to May 1, 2025), Web page, ss. 5, 9, 10, 14. Accessed 2026-11-04.
General information based on the official sources listed above, not legal, tax or engineering advice. Rules change; check the source or ask a qualified professional before you act.