More for you →

Material suppliers have 60 days after their last supply to register a lien.

What changes

Manitoba's prompt payment regime was proclaimed in stages. Specified sections took effect November 14 and 15, 2024, and the rest on April 1, 2025. An owner must pay a proper invoice within 28 days, or give a notice of non-payment within 14 days (s. 90). A contractor must pay its subcontractors within 7 days of receiving payment (s. 92). If the owner does not pay, the contractor must still pay within 35 days of the invoice, and the deadline moves down the chain by 7 days per tier (ss. 93, 98). An adjudicator's decision binds the parties until a court, arbitration or written agreement decides otherwise (s. 118). A contractor's lien can be registered within 60 days after substantial performance or abandonment (s. 43).

Words with a dotted underline have a short explanation: tap or hover.

Who it affects 4

  • Suppliers Material suppliers have 60 days after their last supply to register a lien.
  • Owners & developers Pay proper invoices within 28 days, or give a notice of non-payment within 14 days.
  • Contractors Pay subcontractors within 7 days of receiving payment. If the owner doesn't pay, you still owe them by day 35.
  • Trades You have statutory payment deadlines, the right to interim-binding adjudication, and 60 days to register a lien.

Not directly affected: homebuyers & customers, workers, designers.