Lien deadlines · New Brunswick
Your deadlines
No date to count from
Change dates · Start again · Plain-language guide
All deadlines in New Brunswick
Under the Construction Remedies Act, S.N.B. 2020, c. 29, read in the official text on November 23, 2026. Not legal advice.
Holdback: 10%
Details · s. 34(1)
Counted from: each payment as services or materials are supplied. Who: owners.
Official words: “shall retain a holdback equal to 10% of the contract price”
Holdback period ends: 60 days
Details · s. 47(1), s. 48(1)
Counted from: the date the certificate of substantial performance is signed or the declaration is made. Who: owner (holdback on the contract and subcontracts).
The owner pays out only when the holdback period has expired AND all liens are extinguished, discharged or otherwise provided for (s. 48(1)).
Official words: “shall be retained for 60 days after the date the certificate of substantial performance is signed or the declaration of substantial performance is made”
Holdback period ends: 60 days
Details · s. 47(2)
Counted from: the contract is completed, abandoned or terminated (no certificate or declaration). Who: owner.
Same payout conditions as above.
Official words: “shall be retained for 60 days after the contract is completed, abandoned or terminated”
Notice to the owner: 45 days
Details · s. 54(4), s. 54(8)
Counted from: the first day services or materials are supplied. Who: contractors on prescribed residential buildings (not Crown or local government owners).
If the contractor misses it, the contractor cannot register a claim for lien (s. 54(8)); subcontractors are not affected (s. 54(9)). Which buildings are covered is set by regulation (not read).
Official words: “shall be given no later than 45 days after the first day services or materials are supplied”
Last day to file a lien: 60 days
Details · s. 59(1)
Counted from: the earlier of: certificate of substantial performance signed / declaration made, or the contract completed, abandoned or terminated. Who: contractors.
Work to complete a substantially performed contract: 60 days after completion, abandonment or termination (s. 59(2)).
Official words: “until the expiry of 60 days after the occurrence of the earlier of the following”
Last day to file a lien: 60 days
Details · s. 60(1)
Counted from: the earliest of: certificate/declaration of substantial performance of the contract; contract completed, abandoned or terminated; subcontractor last supplies; certificate/declaration of completion of its subcontract or a higher subcontract. Who: subcontractors.
Official words: “until the expiry of 60 days after the occurrence of the earliest of the following”
Last day to file a lien: 60 days
Details · s. 61(1)
Counted from: the earliest of: certificate/declaration of substantial performance; contract completed, abandoned or terminated; worker last supplies services; certificate/declaration of completion of the subcontract. Who: workers claiming wages.
Official words: “until the expiry of 60 days after the occurrence of the earliest of the following”
Court action on the lien: 90 days
Details · s. 64(2)
Counted from: the claim for lien is registered in the land registration office. Who: lien claimants (liens that attach to land).
Within 90 days: start an action AND register a certificate of pending litigation. Liens against a public owner's holdback: 90 days after a copy of the claim is given (s. 65(2)).
Official words: “is extinguished 90 days after the claim for lien is registered in the appropriate land registration office”
Court action on the lien: 1 year
Details · s. 66(1)
Counted from: an action to enforce the lien is commenced. Who: lien claimants who have sued.
Unless the action is set down for trial, or a motion to extend that time was made and served (s. 66(1)(a)-(b)).
Official words: “A lien is extinguished one year after an action to enforce it has been commenced unless”
Not for: Which residential buildings need a notice to owner (regulation); public owners' holdback liens; transitional rules for contracts made before the Act; adjudication or prompt payment (not read).