Lien deadlines · Newfoundland and Labrador

Your deadlines

×

No date to count from

Enter a date →

Change dates · Start again · Plain-language guide

All deadlines in Newfoundland and Labrador

Under the Mechanics' Lien Act, R.S.N.L. 1990, c. M-3, read in the official text on November 23, 2026. Not legal advice.

Holdback: 10%

Details · s. 12(1)

Counted from: each payment as work is done or materials provided. Who: the person primarily liable upon the contract.

Large contracts have annual early release (s. 12.1).

Official words: “retain for a period of 30 days after the completion or abandonment of the work done or to be done under the contract 10% of the value”

Holdback period ends: 30 days

Details · s. 12(1), s. 12(7)

Counted from: completion or abandonment of the work under the contract. Who: the person primarily liable (paying the holdback).

Unless proceedings to enforce a lien against the holdback were started in the meantime.

Official words: “after the expiration of the period of 30 days mentioned in subsection (1)”

Last day to file a lien: 30 days

Details · s. 22(1)

Counted from: completion or abandonment of the contract or subcontract. Who: contractors and subcontractors (cases not otherwise provided for).

Official words: “within 30 days after the completion or abandonment of the contract or of the subcontract”

Last day to file a lien: 30 days

Details · s. 22(2)

Counted from: placing or providing of the last material. Who: material suppliers.

Official words: “within 30 days after the placing or providing of the last material so placed or provided”

Last day to file a lien: 30 days

Details · s. 22(3)

Counted from: completion of the service. Who: persons providing services.

Official words: “within 30 days after the completion of the service”

Last day to file a lien: 30 days

Details · s. 22(4)

Counted from: the last work done for which the lien is claimed. Who: workers claiming wages.

Official words: “within 30 days after the last work was done for which the lien is claimed”

Court action on the lien: 90 days

Details · s. 24(1)

Counted from: the work is completed or the materials placed or provided. Who: lien claimants with a registered claim.

Action must be started and a certificate registered (s. 23). Counted from completion, not from registration.

Official words: “stops existing on the expiration of 90 days after the work has been completed or the materials have been placed or provided”

Not for: Large-contract annual release (ss. 12.1-12.4); claims where there is no lien on land (public streets, s. 5 / s. 22(5) notice); court steps and fees.