Lien deadlines · Nunavut
Your deadlines
No date to count from
Change dates · Start again · Plain-language guide
All deadlines in Nunavut
Under the Mechanics Lien Act, C.S.Nu., c. M-30, read in the official text on November 23, 2026. Not legal advice.
Holdback: 10%
Details · s. 6
Counted from: the price to be paid to the contractor. Who: owners (a right to retain, not a duty).
Only 'in the absence of a stipulation to the contrary'.
Official words: “an owner is entitled to retain 10% of the price to be paid to the contractor for a period of 45 days after the completion of the contract”
Holdback period ends: 45 days
Details · s. 6
Counted from: completion of the contract. Who: owners.
This is the period the owner may keep the 10%; the Act does not say the owner must pay on that day.
Official words: “for a period of 45 days after the completion of the contract”
Last day to file a lien: 45 days
Details · s. 21(1)
Counted from: the last day of labour for which the wages are payable. Who: workers claiming wages.
Official words: “must be registered within 45 days after the last day of labour for which the wages are payable”
Last day to file a lien: 45 days
Details · s. 22(a)
Counted from: the day the contract is completed, terminated or abandoned. Who: contractors.
Official words: “within 45 days after the day the contract is completed, terminated or abandoned”
Last day to file a lien: 45 days
Details · s. 22(b)
Counted from: the day the sub-contract is completed, terminated or abandoned. Who: sub-contractors.
Official words: “within 45 days after the day the sub-contract is completed, terminated or abandoned”
Last day to file a lien: 45 days
Details · s. 22(c)
Counted from: the day the last of the materials is furnished or the contract to furnish them is terminated or abandoned. Who: material suppliers.
Official words: “within 45 days after the day that the last of the materials is furnished or the contract to furnish the materials is terminated or abandoned”
Court action on the lien: 45 days
Details · s. 24(1)(a)
Counted from: the last day on which the claim of lien could have been registered under s. 21 or 22. Who: lien claimants with a registered lien.
Start proceedings AND register a certificate of proceedings. If the last registration day falls on a Saturday or holiday, count from the actual last day (s. 24(2)).
Official words: “after 45 days from the last day on which the claim of lien could have been registered under section 21 or 22”
Court action on the lien: 90 days
Details · s. 24(1)(b)
Counted from: the day the period of credit (stated in the registered claim) expires. Who: lien claimants whose claim states a period of credit.
Official words: “after 90 days from the day on which the period of credit expires”
Not for: Machinery liens (s. 22(d)); liens under s. 8; court procedure; whether a contract clause changes the owner's holdback right.