Lien deadlines · Saskatchewan
Your deadlines
No date to count from
Change dates · Start again · Plain-language guide
All deadlines in Saskatchewan
Under the The Builders' Lien Act, S.S. 1984-85-86, c. B-7.1, read in the official text on November 23, 2026. Not legal advice.
Pay the invoice: 28 days
Details · s. 5.4(1)
Counted from: the owner receives the proper invoice from the contractor. Who: owner paying the contractor.
Subject to a notice of non-payment (s. 5.4(2)) and the regulations.
Official words: “no later than 28 days after receiving the proper invoice from the contractor”
Dispute the invoice: 14 days
Details · s. 5.4(2)
Counted from: the owner receives the proper invoice from the contractor. Who: owner disputing a proper invoice.
Notice in the prescribed form, with the amount not paid and all reasons.
Official words: “no later than 14 days after receiving the proper invoice from the contractor, the owner gives to the contractor a notice of non-payment”
Holdback: 10%
Details · s. 34(1)
Counted from: each payment on a contract or subcontract under which a lien may arise. Who: every payer (owner, contractor, subcontractor).
Official words: “shall retain a holdback equal to 10% of the greater of”
Holdback period ends: 40 clear days
Details · s. 43(1)(a)
Counted from: the day a copy of the certificate of substantial performance of the contract is given (s. 41). Who: every payer on the contract and subcontracts.
Must pay then unless a claim of lien is registered (subject to s. 38). Holdback for work after substantial performance: 40 clear days after completion or abandonment (s. 43(1)(b)).
Official words: “40 clear days after the day a copy of the certificate of substantial performance of the contract is given pursuant to section 41”
Holdback period ends: 40 clear days
Details · s. 44
Counted from: the earlier of the day the contract is completed or abandoned (no certificate of substantial performance given). Who: every payer on the contract and subcontracts.
Unless a claim of lien is registered (subject to s. 38).
Official words: “make payment of the holdback, 40 clear days after the earlier of”
Not for: Liens of subcontractors, suppliers and workers (s. 49(3) has several alternative triggers); large contracts over $25,000,000 with annual release (s. 46); adjudication periods and the adjudication lien-extension rule; trust rules; residential specifics.