Information only — not legal advice and not a substitute for a lawyer. Check with a lawyer before you rely on it.
Lien deadlines · Alberta · Step 2 of 4
Who are you on this job?
All deadlines in Alberta
Under the Prompt Payment and Construction Lien Act, R.S.A. 2000, c. P-26.4, read in the official text on November 23, 2026. Not legal advice.
Pay the invoice: 28 days
Details · s. 32.2(1)
Counted from: the owner receives a proper invoice. Who: owner paying the contractor.
Unless a notice of dispute is given in time (s. 32.2(2)); undisputed amounts still due in 28 days (s. 32.2(3)).
Official words: “must pay the amount payable under a proper invoice no later than 28 days after receiving the proper invoice”
Dispute the invoice: 14 days
Details · s. 32.2(2)
Counted from: the owner receives a proper invoice. Who: owner disputing a contractor's proper invoice.
Notice must be in the prescribed form and give the amount not paid and all reasons.
Official words: “no later than 14 days after receiving the proper invoice, the owner gives the contractor a notice of dispute”
Contractor pays subcontractors: 7 days
Details · s. 32.3(1)
Counted from: the contractor receives payment of a proper invoice. Who: contractor paying its subcontractors.
Subject to a notice of non-payment (s. 32.3(6)). Same 7 days for partial payment (s. 32.3(2)).
Official words: “must, no later than 7 days after receiving payment, pay each subcontractor”
Last day to file a lien: 60 days
Details · s. 41(1)(a)
Counted from: the day the last of the materials is furnished or the contract to furnish materials is abandoned. Who: material suppliers.
90 days for oil/gas well work (s. 41(1)(b)) and concrete (s. 41(1)(c)).
Official words: “terminating 60 days from the day that the last of the materials is furnished or the contract to furnish the materials is abandoned”
Last day to file a lien: 60 days
Details · s. 41(2)(a)
Counted from: the day the performance of the services is completed or the contract to provide them is abandoned. Who: persons providing services.
90 days for oil/gas well work and concrete (s. 41(2)(b), (c)).
Official words: “terminating 60 days from the day that the performance of the services is completed or the contract to provide the services is abandoned”
Last day to file a lien: 60 days
Details · s. 41(3)(a)
Counted from: the day the work for which wages are claimed is completed or abandoned. Who: workers claiming wages.
90 days for oil/gas well work and concrete (s. 41(3)(b), (c)).
Official words: “terminating 60 days from the day that the work for which the wages are claimed is completed or abandoned”
Last day to file a lien: 60 days
Details · s. 41(4)(a)
Counted from: the day the contract or subcontract is completed or abandoned. Who: contractors and subcontractors (cases not in s. 41(1)-(3)).
Fixing defects later does not extend the period (s. 41(5)).
Official words: “terminating 60 days from the day the contract or subcontract, as the case may be, is completed or abandoned”
Last day to file a lien: 90 days
Details · s. 41(4)(c)
Counted from: the day the contract or subcontract is completed or abandoned. Who: contractors and subcontractors on improvements primarily related to concrete.
Concrete special case. Same 90 days for concrete materials, services and wages (s. 41(1)(c), (2)(c), (3)(c)).
Official words: “in relation to concrete, terminating 90 days from the day the contract or subcontract, as the case may be, is completed or abandoned”
Last day to file a lien: 90 days
Details · s. 41(4)(b)
Counted from: the day the contract or subcontract is completed or abandoned. Who: contractors and subcontractors on oil or gas well / well site improvements.
Oil/gas special case. Same 90 days for materials, services and wages (s. 41(1)(b), (2)(b), (3)(b)).
Official words: “gas well site, terminating 90 days from the day the contract or subcontract, as the case may be, is completed or abandoned”
Court action on the lien: 180 days
Details · s. 43(1)
Counted from: the date the lien is registered. Who: lien claimants with a registered lien.
Within 180 days: start an action AND register a certificate of lis pendens.
Official words: “A lien that has been registered ceases to exist unless, within 180 days from the date it is registered”
Not for: Public works under the Public Works Act; adjudication periods; holdback trust rules; residential/consumer contract rules; which date counts as completion (user enters it); minimum lien amount and Land Titles filing steps.