Lien deadlines · British Columbia · Step 2 of 3
Who are you on this job?
All deadlines in British Columbia
Under the Builders Lien Act, S.B.C. 1997, c. 45, read in the official text on November 23, 2026. Not legal advice.
Holdback: 10%
Details · s. 4(1)
Counted from: each payment on a contract or subcontract under which a lien may arise. Who: the person primarily liable on each contract and subcontract (owner, contractor, subcontractor).
10% of the greater of (a) the value of work or material actually provided and (b) any payment made on account.
Official words: “must retain a holdback equal to 10% of the greater of”
Last day to file a lien: 45 days
Details · s. 20(1)
Counted from: the date the certificate of completion was issued for the contract or subcontract. Who: the contractor or subcontractor named in the certificate, and anyone engaged by or under them.
A later certificate does not extend or restart a period that has already started (s. 20(3)).
Official words: “may be filed no later than 45 days after the date on which the certificate of completion was issued”
Last day to file a lien: 45 days
Details · s. 20(2)
Counted from: the head contract is completed, abandoned or terminated (if the owner engaged a head contractor); otherwise the improvement is completed or abandoned. Who: all lien claimants not covered by a certificate of completion.
Use only when no certificate of completion was issued for the claimant's contract or subcontract.
Official words: “A claim of lien that is not governed by subsection (1) may be filed no later than 45 days after”
Holdback period ends: 55 days
Details · s. 8(1), s. 8(4)
Counted from: the date the certificate of completion was issued. Who: holdback on that contract or subcontract and any subcontract under it.
After the holdback period ends the holdback may be paid (s. 8(4)), unless a claim of lien was filed or lien proceedings were started in the meantime.
Official words: “expires at the end of 55 days after the certificate of completion is issued”
Holdback period ends: 55 days
Details · s. 8(2), s. 8(4)
Counted from: the head contract is completed, abandoned or terminated (if the owner engaged a head contractor); otherwise the improvement is completed or abandoned. Who: holdback on contracts and subcontracts without a certificate of completion.
Payment after the period discharges liens unless a claim of lien was filed or proceedings started in the meantime (s. 8(4)).
Official words: “The holdback period for a contract or subcontract that is not governed by subsection (1) expires at the end of 55 days after”
Court action on the lien: 1 year
Details · s. 33(1)
Counted from: the date the claim of lien was filed. Who: lien claimants who filed a claim of lien.
Within 1 year the claimant must start an action AND register a certificate of pending litigation.
Official words: “not later than one year from the date of its filing”
Court action on the lien: 21 days
Details · s. 33(2)
Counted from: service of a notice to commence an action (served by the owner or by a lien claimant who has sued). Who: lien claimants served with the notice.
Shortens the 1-year period. Mailed notice is deemed served on the 8th day after mailing (s. 33(4)).
Official words: “pending litigation within 21 days after service of the notice”
Not for: Prompt payment (no prompt payment periods in this table for BC); holdback trust/holdback account rules; certifier requests (s. 7); whether and when a contract counts as completed (the user must enter that date); Crown/government land; mineral titles; filing procedure and fees.