Information only — not legal advice and not a substitute for a lawyer. Check with a lawyer before you rely on it.
Lien deadlines · Manitoba · Step 2 of 3
Who are you on this job?
All deadlines in Manitoba
Under the The Builders' Liens Act, C.C.S.M. c. B91, read in the official text on November 23, 2026. Not legal advice.
Pay the invoice: 28 days
Details · s. 90(1)
Counted from: the proper invoice is given to the owner by the contractor. Who: owner paying the contractor.
The Act's own example: invoice July 1, pay by July 29. Prompt payment applies only to contracts entered into on or after the Division came into force (s. 80(1)).
Official words: “an owner must pay the invoiced amount within 28 days after the proper invoice is given to the owner by the contractor”
Dispute the invoice: 14 days
Details · s. 90(2)
Counted from: the proper invoice is given to the owner. Who: owner disputing the invoice.
Form and contents set by s. 90(3) and the regulations.
Official words: “if the owner gives a notice of non-payment to the contractor within 14 days after the invoice is given to the owner”
Contractor pays subcontractors: 7 days
Details · s. 92(1)
Counted from: the contractor receives payment of all or part of the invoiced amount. Who: contractor paying applicable sub-contractors.
Official words: “must pay the amount received for each applicable sub-contractor within 7 days after receiving payment”
Contractor pays subcontractors: 35 days
Details · s. 93(1)
Counted from: the contractor gives the proper invoice to the owner (applies if the owner does not pay in full within 28 days). Who: contractor paying applicable sub-contractors.
Exceptions for notices of non-payment are in the Act (ss. 93-95).
Official words: “within 35 days after giving the proper invoice to the owner”
Holdback period ends: 60 days
Details · s. 24(1), s. 27(3)
Counted from: the earliest of: a certificate of substantial performance is given (s. 46), the contract is completed, or the contract is abandoned. Who: the person primarily liable (paying the holdback).
Only if no liens are registered against the land when the holdback is paid (s. 27(3)).
Official words: “may be validly made after the expiration of 60 days mentioned in subsection 24(1) or (2)”
Last day to file a lien: 60 days
Details · s. 43(1)
Counted from: substantial performance or abandonment of the contract. Who: contractors.
Exceptions in s. 44 (e.g. work to complete a substantially performed contract).
Official words: “within 60 days after the substantial performance or abandonment of the contract”
Last day to file a lien: 60 days
Details · s. 43(2)
Counted from: whichever first occurs: substantial performance or abandonment of the contract, or of the sub-contract. Who: sub-contractors.
Exceptions in s. 44.
Official words: “within 60 days after the substantial performance or abandonment of the sub-contract”
Last day to file a lien: 60 days
Details · s. 43(3)
Counted from: whichever first occurs: substantial performance or abandonment of the contract, or the supply of the last materials. Who: material suppliers.
Exceptions in s. 44.
Official words: “within 60 days after the supplying of the last materials so supplied”
Last day to file a lien: 60 days
Details · s. 43(4)
Counted from: whichever first occurs: substantial performance or abandonment of the contract, or completion of the services. Who: persons providing services.
Exceptions in s. 44.
Official words: “within 60 days after the completion of the provision of the services”
Last day to file a lien: 60 days
Details · s. 43(5)
Counted from: whichever first occurs: substantial performance or abandonment of the contract, or the last work done / services provided. Who: workers claiming wages.
Exceptions in s. 44.
Official words: “within 60 days after the last work was done or the last services were provided”
Not for: Contracts made before the prompt payment Division came into force (s. 80(1)); sub-contractor-to-sub-contractor payments (ss. 97-100); adjudication; lien action deadlines; s. 44 exceptions; older 40-day guidance.