Lien deadlines · Nova Scotia · Step 2 of 3

Who are you on this job?

×
All deadlines in Nova Scotia

Under the Builders' Lien Act, R.S.N.S. 1989, c. 277, read in the official text on November 23, 2026. Not legal advice.

Holdback: 10%

Details · s. 13(2)

Counted from: each payment as work is done or materials are furnished. Who: the person primarily liable upon the contract.

Separate 10% holdback for work after substantial performance (s. 13(3)).

Official words: “retain for a period of sixty days after the contract is substantially performed, ten per cent of the value”

Holdback period ends: 60 days

Details · s. 13(2), s. 13(6)

Counted from: the contract is substantially performed. Who: the person primarily liable (paying the holdback).

Unless proceedings to enforce a lien against the holdback have been started in the meantime. Interest at prime + 2% if not paid within 65 days (s. 13(8)).

Official words: “may be validly made so as to discharge all liens or charges in respect thereof after the expiration of the periods mentioned in subsections (2) and (3)”

Last day to file a lien: 60 days

Details · s. 24(1)

Counted from: completion or abandonment of the contract. Who: contractors and subcontractors (cases not otherwise provided for).

Official words: “or within sixty days after the completion or abandonment thereof”

Last day to file a lien: 60 days

Details · s. 24(2)

Counted from: the furnishing or placing of the last material. Who: material suppliers.

Official words: “or within sixty days after the furnishing or placing of the last material so furnished or placed”

Last day to file a lien: 60 days

Details · s. 24(3)

Counted from: completion of the service. Who: persons providing services.

Official words: “or within sixty days after the completion of the service”

Last day to file a lien: 60 days

Details · s. 24(4)

Counted from: the last work done for which the lien is claimed. Who: workers claiming wages.

Official words: “or within sixty days after the last work is done for which the lien is claimed”

Last day to file a lien: 7 days

Details · s. 24(5)

Counted from: the architect, engineer or other certifier gives, or refuses on the contractor's application to give, a final certificate. Who: contractors on contracts supervised by a payment certifier.

Alternative to the 60 days in s. 24(1) (the Act says 'within the time mentioned in subsection (1) or within seven days after'). For these liens the action deadline is 30 days from registration (s. 26(1)).

Official words: “within seven days after the architect, engineer or other person has given, or has, upon application to him by the contractor, refused to give a final certificate”

Court action on the lien: 105 days

Details · s. 26(1)

Counted from: the work or service is completed or materials furnished or placed, or the expiry of the period of credit. Who: lien claimants with a registered claim.

Action must be started and a certificate (Form E / certificate of lis pendens) registered. Read together with s. 27 (90 days where there is no period of credit) Which one applies depends on the facts: check both.

Official words: “on the expiration of one hundred and five days after the work or service has been completed or materials have been furnished or placed, or after the expiry of the period of credit”

Court action on the lien: 90 days

Details · s. 27

Counted from: the work or service is completed or materials furnished or placed (no period of credit, or credit expiry date not stated in the claim). Who: lien claimants with a registered claim.

Action must be started and a certificate registered as in s. 26.

Official words: “the lien shall cease to exist upon the expiration of ninety days after the work or service has been completed or materials furnished or placed”

Not for: Prompt payment (amendments not in force are not in the consolidation); periods of credit longer than 6 months (s. 26(2)); public streets and highways; court steps and fees.