Lien deadlines · Northwest Territories · Step 2 of 3
Who are you on this job?
All deadlines in Northwest Territories
Under the Builders' Lien Act, S.N.W.T. 2023, c. 24, read in the official text on November 23, 2026. Not legal advice.
Holdback: 10%
Details · s. 24(1)
Counted from: services or materials as actually supplied. Who: every payer on a contract or subcontract.
Kept until all liens against it have expired or been dealt with. Separate 10% holdback for finishing work (s. 24(2)).
Official words: “retain a holdback equal to 10% of the price of the services or materials”
Last day to file a lien: 60 days
Details · s. 36(2)(a)
Counted from: the earlier of: a copy of the certificate or declaration of substantial performance is published (s. 37), or the contract is completed, abandoned or terminated. Who: contractors (services or materials supplied on or before substantial performance).
Unless preserved (s. 45) within the period.
Official words: “expires at the conclusion of the 60-day period following the earlier of”
Last day to file a lien: 60 days
Details · s. 36(2)(b)
Counted from: the earlier of: the contract is completed, or abandoned or terminated (no certificate, or supply after substantial performance). Who: contractors.
Unless preserved (s. 45).
Official words: “expires at the conclusion of the 60-day period following the earlier of”
Last day to file a lien: 60 days
Details · s. 36(4)(b)
Counted from: the earlier of: the person last supplied services or materials; the contract completed, abandoned or terminated; the subcontract certified complete (s. 44) (no certificate of substantial performance, or supply after it). Who: subcontractors, suppliers and other non-contractor claimants.
Before substantial performance, publication of the certificate is also a trigger (s. 36(4)(a)). Unless preserved (s. 45).
Official words: “the 60-day period following the occurrence of the earlier of”
Court action on the lien: 90 days
Details · s. 47(2)
Counted from: the last day under s. 36 on which the lien could have been preserved. Who: lien claimants with a preserved lien.
Perfect = start an action and register a certificate of pending litigation (s. 47(3)).
Official words: “expires unless it is perfected prior to the end of the 90-day period next following the last day under section 36, when the lien could have been preserved”
Not for: Contracts signed before September 1, 2025 (old Mechanics Lien Act, per the GNWT news release); homes and home buyers special rules; workers' trust fund liens; trust provisions; forms and regulations.