Lien deadlines · Ontario · Step 2 of 3
Who are you on this job?
All deadlines in Ontario
Under the Construction Act, R.S.O. 1990, c. C.30, read in the official text on November 23, 2026. Not legal advice.
Pay the invoice: 28 days
Details · s. 6.4(1)
Counted from: the owner receives the proper invoice from the contractor. Who: owner paying the contractor.
Subject to a notice of non-payment (s. 6.4(2)).
Official words: “an owner shall pay the amount payable under a proper invoice no later than 28 days after receiving the proper invoice from the contractor”
Dispute the invoice: 14 days
Details · s. 6.4(2)
Counted from: the owner receives the proper invoice from the contractor. Who: owner disputing a proper invoice.
Prescribed form; amount not paid and all reasons.
Official words: “no later than 14 days after receiving the proper invoice from the contractor, the owner gives to the contractor a notice of non-payment”
Contractor pays subcontractors: 7 days
Details · s. 6.5(1)
Counted from: the contractor receives full payment of the proper invoice. Who: contractor paying subcontractors.
Partial payment: also 7 days (s. 6.5(2)). If the owner does not pay: 35 days after giving the invoice (s. 6.5(4)), unless notice given.
Official words: “shall, no later than seven days after receiving payment, pay each subcontractor”
Holdback: 10%
Details · s. 22(1)
Counted from: services or materials as actually supplied. Who: each payer on a contract or subcontract.
Official words: “shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied”
Last day to file a lien: 60 days
Details · s. 31(2)(a)
Counted from: the earlier of: a copy of the certificate or declaration of substantial performance is published (s. 32), or the contract is completed, abandoned or terminated. Who: contractors (supply on or before substantial performance).
Lien must be preserved (s. 34) within this period. A published notice of termination sets the termination date (s. 31(6)-(7)).
Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”
Last day to file a lien: 60 days
Details · s. 31(2)(b)
Counted from: the earlier of: the contract is completed, or abandoned or terminated (no certificate, or supply after substantial performance). Who: contractors.
Preserve under s. 34.
Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”
Last day to file a lien: 60 days
Details · s. 31(3)(b)
Counted from: the earlier of: the person last supplied services or materials; the contract completed, abandoned or terminated; the subcontract certified complete (s. 33) (no certificate, or supply after substantial performance). Who: subcontractors, suppliers and other non-contractor claimants.
Before substantial performance, publication of the certificate is also a trigger (s. 31(3)(a)). Preserve under s. 34.
Official words: “the date on which the person last supplied services or materials to the improvement”
Court action on the lien: 90 days
Details · s. 36(2)
Counted from: the last day under s. 31 on which the lien could have been preserved. Who: lien claimants with a preserved lien.
Perfect = start an action and register a certificate of action (s. 36(3)).
Official words: “expires unless it is perfected prior to the end of the 90-day period next following the last day, under section 31, on which the lien could have been preserved”
Not for: Holdback release (annual release and payment rules in s. 26 are multi-step); contracts governed by older versions of the Act under its transition rules (not checked); workers' trust fund liens; adjudication; municipal/public-private contracts; ON is not in a reviewed ArtBuild article.