Lien deadlines · Prince Edward Island · Step 2 of 3

Who are you on this job?

×
All deadlines in Prince Edward Island

Under the Mechanics' Lien Act, R.S.P.E.I. 1988, c. M-4, read in the government text on November 23, 2026. Not legal advice.

Source: Unofficial office consolidation by the PEI Legislative Counsel Office, current to January 1, 2009 (the only text on the government site). Later amendments could not be checked.

Holdback: 20%

Details · s. 14(1)

Counted from: each payment by the owner on a contract under which a lien may arise. Who: owners.

Where the value of the work and material exceeds $15,000 the holdback is fifteen per cent instead, but never less than on a $15,000 job (s. 14(3)).

Official words: “an amount equal to twenty per cent of the value of the work done and of the material furnished to be used”

Holdback period ends: 60 days

Details · s. 14(1)

Counted from: the completion or abandonment of the contract. Who: owners holding the holdback.

Payment of the holdback is governed by s. 16 (no claim of lien registered and no action started).

Official words: “retain for a period of sixty days after the completion or abandonment of the contract”

Last day to file a lien: 60 days

Details · s. 24(1)

Counted from: the last work for which the wages are owing. Who: workers claiming wages.

Official words: “may be registered at any time before the expiration of sixty days from the doing of the last work for which the wages are owing”

Last day to file a lien: 60 days

Details · s. 24(2)

Counted from: the completion of the services. Who: persons who provided services.

Official words: “may be registered at any time before the expiration of sixty days from the completion of the services”

Last day to file a lien: 60 days

Details · s. 24(3)

Counted from: the furnishing of the last material claimed for. Who: suppliers of material.

Official words: “may be registered at any time before the expiration of sixty days from the furnishing of the last material the price of which is claimed for”

Last day to file a lien: 60 days

Details · s. 24(4)

Counted from: the completion or abandonment of the contract or sub-contract. Who: contractors and sub-contractors.

Where an architect or engineer certifies payments, the contractor may also register within seven days after a final certificate is given or refused (s. 24(5)).

Official words: “be registered at any time before the expiration of sixty days from the completion or abandonment of the contract or sub-contract”

Court action on the lien: 90 days

Details · s. 27

Counted from: the date the claim of lien is registered. Who: lien claimants with a registered claim.

The owner can shorten this with a 30-day notice under s. 28.

Official words: “ceases to exist on the expiration of ninety days from the registration of the claim of lien unless, in the meantime, an action is commenced”

Not for: Changes made after January 1, 2009; the 7-day final-certificate option (s. 24(5)); notices under s. 28.