Information only — not legal advice and not a substitute for a lawyer. Check with a lawyer before you rely on it.

Lien deadlines · British Columbia

Your deadlines

×

No date to count from

Enter a date →

Change dates · Start again · Plain-language guide

All deadlines in British Columbia

Under the Builders Lien Act, S.B.C. 1997, c. 45, read in the official text on November 23, 2026. Not legal advice.

Holdback: 10%

Details · s. 4(1)

Counted from: each payment on a contract or subcontract under which a lien may arise. Who: the person primarily liable on each contract and subcontract (owner, contractor, subcontractor).

10% of the greater of (a) the value of work or material actually provided and (b) any payment made on account.

Official words: “must retain a holdback equal to 10% of the greater of”

Last day to file a lien: 45 days

Details · s. 20(1)

Counted from: the date the certificate of completion was issued for the contract or subcontract. Who: the contractor or subcontractor named in the certificate, and anyone engaged by or under them.

A later certificate does not extend or restart a period that has already started (s. 20(3)).

Official words: “may be filed no later than 45 days after the date on which the certificate of completion was issued”

Last day to file a lien: 45 days

Details · s. 20(2)

Counted from: the head contract is completed, abandoned or terminated (if the owner engaged a head contractor); otherwise the improvement is completed or abandoned. Who: all lien claimants not covered by a certificate of completion.

Use only when no certificate of completion was issued for the claimant's contract or subcontract.

Official words: “A claim of lien that is not governed by subsection (1) may be filed no later than 45 days after”

Holdback period ends: 55 days

Details · s. 8(1), s. 8(4)

Counted from: the date the certificate of completion was issued. Who: holdback on that contract or subcontract and any subcontract under it.

After the holdback period ends the holdback may be paid (s. 8(4)), unless a claim of lien was filed or lien proceedings were started in the meantime.

Official words: “expires at the end of 55 days after the certificate of completion is issued”

Holdback period ends: 55 days

Details · s. 8(2), s. 8(4)

Counted from: the head contract is completed, abandoned or terminated (if the owner engaged a head contractor); otherwise the improvement is completed or abandoned. Who: holdback on contracts and subcontracts without a certificate of completion.

Payment after the period discharges liens unless a claim of lien was filed or proceedings started in the meantime (s. 8(4)).

Official words: “The holdback period for a contract or subcontract that is not governed by subsection (1) expires at the end of 55 days after”

Court action on the lien: 1 year

Details · s. 33(1)

Counted from: the date the claim of lien was filed. Who: lien claimants who filed a claim of lien.

Within 1 year the claimant must start an action AND register a certificate of pending litigation.

Official words: “not later than one year from the date of its filing”

Court action on the lien: 21 days

Details · s. 33(2)

Counted from: service of a notice to commence an action (served by the owner or by a lien claimant who has sued). Who: lien claimants served with the notice.

Shortens the 1-year period. Mailed notice is deemed served on the 8th day after mailing (s. 33(4)).

Official words: “pending litigation within 21 days after service of the notice”

Not for: Prompt payment (no prompt payment periods in this table for BC); holdback trust/holdback account rules; certifier requests (s. 7); whether and when a contract counts as completed (the user must enter that date); Crown/government land; mineral titles; filing procedure and fees.