Lien deadlines · Prince Edward Island
Your deadlines
Prince Edward Island rules as published in 2009. Later changes could not be checked — confirm with a lawyer or the Province before relying on a date.
No date to count from
Change dates · Start again · Plain-language guide
All deadlines in Prince Edward Island
Under the Mechanics' Lien Act, R.S.P.E.I. 1988, c. M-4, read in the government text on November 23, 2026. Not legal advice.
Source: Unofficial office consolidation by the PEI Legislative Counsel Office, current to January 1, 2009 (the only text on the government site). Later amendments could not be checked.
Holdback: 20%
Details · s. 14(1)
Counted from: each payment by the owner on a contract under which a lien may arise. Who: owners.
Where the value of the work and material exceeds $15,000 the holdback is fifteen per cent instead, but never less than on a $15,000 job (s. 14(3)).
Official words: “an amount equal to twenty per cent of the value of the work done and of the material furnished to be used”
Holdback period ends: 60 days
Details · s. 14(1)
Counted from: the completion or abandonment of the contract. Who: owners holding the holdback.
Payment of the holdback is governed by s. 16 (no claim of lien registered and no action started).
Official words: “retain for a period of sixty days after the completion or abandonment of the contract”
Last day to file a lien: 60 days
Details · s. 24(1)
Counted from: the last work for which the wages are owing. Who: workers claiming wages.
Official words: “may be registered at any time before the expiration of sixty days from the doing of the last work for which the wages are owing”
Last day to file a lien: 60 days
Details · s. 24(2)
Counted from: the completion of the services. Who: persons who provided services.
Official words: “may be registered at any time before the expiration of sixty days from the completion of the services”
Last day to file a lien: 60 days
Details · s. 24(3)
Counted from: the furnishing of the last material claimed for. Who: suppliers of material.
Official words: “may be registered at any time before the expiration of sixty days from the furnishing of the last material the price of which is claimed for”
Last day to file a lien: 60 days
Details · s. 24(4)
Counted from: the completion or abandonment of the contract or sub-contract. Who: contractors and sub-contractors.
Where an architect or engineer certifies payments, the contractor may also register within seven days after a final certificate is given or refused (s. 24(5)).
Official words: “be registered at any time before the expiration of sixty days from the completion or abandonment of the contract or sub-contract”
Court action on the lien: 90 days
Details · s. 27
Counted from: the date the claim of lien is registered. Who: lien claimants with a registered claim.
The owner can shorten this with a 30-day notice under s. 28.
Official words: “ceases to exist on the expiration of ninety days from the registration of the claim of lien unless, in the meantime, an action is commenced”
Not for: Changes made after January 1, 2009; the 7-day final-certificate option (s. 24(5)); notices under s. 28.