Ontario Construction Act deadlines: 28-day payment, 10% holdback, 60 days to preserve a lien

In short: Ontario Construction Act deadlines in plain words: owner pays a proper invoice in 28 days, 14-day notice of non-payment, 7 days to subs, 10% holdback, 60-day lien.

Nov 24, 2026

Before you start: check these

0 of 6 done

Under Ontario's Construction Act, an owner must pay a proper invoice no later than 28 days after receiving it, unless the owner gives a notice of non-payment within 14 days. A contractor who is paid must pay its subcontractors within 7 days. Every payer must retain a 10% holdback. A lien expires if it is not preserved within 60 days of the event that starts the clock, and a preserved lien expires if it is not perfected within 90 days after the last day it could have been preserved.

The section numbers below point to the official e-Laws text so you can check each rule yourself. If you want the dates worked out for a specific job, ArtBuild's free lien deadline calculator does the counting; treat its result as a starting point, not as legal advice.

Step 1: a proper invoice starts the payment clock (ss. 6.1, 6.3, 6.4)

The prompt payment rules are in Part I.1. They start with a proper invoice: a written bill or other request for payment that contains the information listed in s. 6.1(1), including the contractor's name and address, the invoice date and the period or milestone it covers, a description of what was supplied, the amount payable and the payment terms, and who payment goes to. If something is missing, the invoice is still deemed proper unless the owner tells the contractor in writing, within seven days of receiving it, what is wrong and what is needed to fix it (s. 6.1(2)). Unless the contract says otherwise, proper invoices are given monthly (s. 6.3(1)). A contract term that makes giving the invoice depend on a payment certifier's or the owner's prior approval has no effect (s. 6.3(2)). Once the owner receives the proper invoice, s. 6.4(1) gives the owner 28 days to pay it. Payments under this Part are still subject to holdback (s. 6.2).

Step 2: disputing an invoice means a written notice within 14 days (s. 6.4(2), (3))

An owner who disagrees with a proper invoice cannot simply stay silent. To refuse payment of all or part of it, the owner must give the contractor a notice of non-payment no later than 14 days after receiving the invoice. The notice must be in the prescribed form and manner, state the amount not being paid and set out all of the reasons. Any part of the invoice the notice does not cover still has to be paid within the 28 days (s. 6.4(3)). For a contractor, the practical lesson is to note the date the owner received each invoice: if day 14 passes with no notice, the full 28-day obligation stands.

Step 3: money moves down the chain within 7 days (ss. 6.5, 6.6)

When a contractor receives full payment of a proper invoice on time, it must pay each subcontractor whose services or materials were included in that invoice no later than seven days after receiving the money (s. 6.5(1)). A partial payment from the owner is passed down within the same seven days, shared as s. 6.5(3) describes (s. 6.5(2)). If the owner does not pay, the contractor must still pay its subcontractors no later than 35 days after giving the invoice to the owner (s. 6.5(4)), unless it gives them its own notice of non-payment on time. That notice can say the owner has not paid and include an undertaking to refer the matter to adjudication within 21 days (s. 6.5(5)), or it can dispute the subcontractor's entitlement and give reasons (s. 6.5(6)). The timing is set by s. 6.5(7). Section 6.6 applies similar seven-day rules from one subcontractor to the next.

Step 4: the 10% holdback (s. 22)

Each payer on a contract or subcontract under which a lien may arise must retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied (s. 22(1)). The money stays retained until all liens that may be claimed against it have expired or been satisfied, discharged or otherwise provided for. If a contract is certified or declared substantially performed but finishing work remains, a separate 10 per cent holdback applies to that remaining work (s. 22(2)). The duty applies whether the contract pays in instalments or at the end (s. 22(3)), and s. 22(4) allows some or all of a holdback to take the form of a letter of credit or a demand-worded holdback repayment bond in the prescribed form, or any other prescribed form.

Step 5: preserve within 60 days, perfect within 90 more (ss. 31, 34, 36)

A lien expires unless it is preserved (s. 31(1)). For a contractor, the 60-day period for work supplied up to substantial performance runs from the earlier of the publication of the certificate or declaration of substantial performance under s. 32 and the date the contract is completed, abandoned or terminated (s. 31(2)(a)). Where there is no such certificate, or for work after substantial performance, it runs from completion, abandonment or termination of the contract (s. 31(2)(b)). For everyone else, such as subcontractors and suppliers, the 60 days run from the earliest of publication of the certificate, the date the person last supplied services or materials, the date the contract is completed, abandoned or terminated, and the date their subcontract is certified complete under s. 33 (s. 31(3)). Workers' trust funds have their own list in s. 31(2.1). Preserving usually means registering a claim for lien on title in the land registry office, or giving the owner a copy where the lien does not attach to the premises (s. 34(1)). Then the second clock starts: a preserved lien expires unless it is perfected before the end of the 90-day period after the last day it could have been preserved (s. 36(2)), usually by starting an action and registering a certificate of action (s. 36(3)).

Adjudication, transition rules and counting days

Payment fights do not always have to go to court. Part II.1, Construction Dispute Interim Adjudication, lets a party to a contract or subcontract refer a dispute about a prescribed matter, or a matter the parties agree on, to an adjudicator (s. 13.5(1), (2)). For a contract, the notice of adjudication cannot be given more than 90 days after the contract is completed, abandoned or terminated unless the parties agree otherwise (s. 13.5(3)); s. 13.5(3.1) sets the subcontract version. A dispute can go to adjudication even while a court action or arbitration on it is under way, unless that case has been finally decided (s. 13.5(5)). Older projects may follow older rules: s. 87.3 keeps the earlier version of the Act for some improvements with contracts or procurement started before July 1, 2018, and s. 87.4 deals with the amendments in force from January 1, 2026. Finally, a deadline that lands on a weekend or holiday may move under general Ontario rules on counting time; check that before you rely on the last possible day, and get legal advice before registering a lien.

Work out your deadlines

Need a pro for this?

What next?

References

  1. Government of Ontario (Ontario e-Laws). Construction Act, R.S.O. 1990, c. C.30, Current consolidation, period from January 1, 2026 to the e-Laws currency date (last amendment 2025, c. 14, Sched. 2); read as JSON from the e-Laws API because the ontario.ca/laws page blocks plain fetches, ss. 6.1, 6.2, 6.3, 6.4, 6.5, 6.6, 13.5 (Part II.1), 22, 31, 34, 36, 87.3, 87.4. Accessed 2026-11-23.

General information based on the official sources listed above, not legal, tax or engineering advice. Rules change; check the source or ask a qualified professional before you act.