Lien deadlines · Ontario
Your deadlines
No date to count from
Change dates · Start again · Plain-language guide
All deadlines in Ontario
Under the Construction Act, R.S.O. 1990, c. C.30, read in the official text on November 23, 2026. Not legal advice.
Pay the invoice: 28 days
Details · s. 6.4(1)
Counted from: the owner receives the proper invoice from the contractor. Who: owner paying the contractor.
Subject to a notice of non-payment (s. 6.4(2)).
Official words: “an owner shall pay the amount payable under a proper invoice no later than 28 days after receiving the proper invoice from the contractor”
Dispute the invoice: 14 days
Details · s. 6.4(2)
Counted from: the owner receives the proper invoice from the contractor. Who: owner disputing a proper invoice.
Prescribed form; amount not paid and all reasons.
Official words: “no later than 14 days after receiving the proper invoice from the contractor, the owner gives to the contractor a notice of non-payment”
Contractor pays subcontractors: 7 days
Details · s. 6.5(1)
Counted from: the contractor receives full payment of the proper invoice. Who: contractor paying subcontractors.
Partial payment: also 7 days (s. 6.5(2)). If the owner does not pay: 35 days after giving the invoice (s. 6.5(4)), unless notice given.
Official words: “shall, no later than seven days after receiving payment, pay each subcontractor”
Holdback: 10%
Details · s. 22(1)
Counted from: services or materials as actually supplied. Who: each payer on a contract or subcontract.
Official words: “shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied”
Last day to file a lien: 60 days
Details · s. 31(2)(a)
Counted from: the earlier of: a copy of the certificate or declaration of substantial performance is published (s. 32), or the contract is completed, abandoned or terminated. Who: contractors (supply on or before substantial performance).
Lien must be preserved (s. 34) within this period. A published notice of termination sets the termination date (s. 31(6)-(7)).
Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”
Last day to file a lien: 60 days
Details · s. 31(2)(b)
Counted from: the earlier of: the contract is completed, or abandoned or terminated (no certificate, or supply after substantial performance). Who: contractors.
Preserve under s. 34.
Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”
Last day to file a lien: 60 days
Details · s. 31(3)(b)
Counted from: the earlier of: the person last supplied services or materials; the contract completed, abandoned or terminated; the subcontract certified complete (s. 33) (no certificate, or supply after substantial performance). Who: subcontractors, suppliers and other non-contractor claimants.
Before substantial performance, publication of the certificate is also a trigger (s. 31(3)(a)). Preserve under s. 34.
Official words: “the date on which the person last supplied services or materials to the improvement”
Court action on the lien: 90 days
Details · s. 36(2)
Counted from: the last day under s. 31 on which the lien could have been preserved. Who: lien claimants with a preserved lien.
Perfect = start an action and register a certificate of action (s. 36(3)).
Official words: “expires unless it is perfected prior to the end of the 90-day period next following the last day, under section 31, on which the lien could have been preserved”
Not for: Holdback release (annual release and payment rules in s. 26 are multi-step); contracts governed by older versions of the Act under its transition rules (not checked); workers' trust fund liens; adjudication; municipal/public-private contracts; ON is not in a reviewed ArtBuild article.