Lien deadlines · Ontario

Your deadlines

×

No date to count from

Enter a date →

Change dates · Start again · Plain-language guide

All deadlines in Ontario

Under the Construction Act, R.S.O. 1990, c. C.30, read in the official text on November 23, 2026. Not legal advice.

Pay the invoice: 28 days

Details · s. 6.4(1)

Counted from: the owner receives the proper invoice from the contractor. Who: owner paying the contractor.

Subject to a notice of non-payment (s. 6.4(2)).

Official words: “an owner shall pay the amount payable under a proper invoice no later than 28 days after receiving the proper invoice from the contractor”

Dispute the invoice: 14 days

Details · s. 6.4(2)

Counted from: the owner receives the proper invoice from the contractor. Who: owner disputing a proper invoice.

Prescribed form; amount not paid and all reasons.

Official words: “no later than 14 days after receiving the proper invoice from the contractor, the owner gives to the contractor a notice of non-payment”

Contractor pays subcontractors: 7 days

Details · s. 6.5(1)

Counted from: the contractor receives full payment of the proper invoice. Who: contractor paying subcontractors.

Partial payment: also 7 days (s. 6.5(2)). If the owner does not pay: 35 days after giving the invoice (s. 6.5(4)), unless notice given.

Official words: “shall, no later than seven days after receiving payment, pay each subcontractor”

Holdback: 10%

Details · s. 22(1)

Counted from: services or materials as actually supplied. Who: each payer on a contract or subcontract.

Official words: “shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied”

Last day to file a lien: 60 days

Details · s. 31(2)(a)

Counted from: the earlier of: a copy of the certificate or declaration of substantial performance is published (s. 32), or the contract is completed, abandoned or terminated. Who: contractors (supply on or before substantial performance).

Lien must be preserved (s. 34) within this period. A published notice of termination sets the termination date (s. 31(6)-(7)).

Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”

Last day to file a lien: 60 days

Details · s. 31(2)(b)

Counted from: the earlier of: the contract is completed, or abandoned or terminated (no certificate, or supply after substantial performance). Who: contractors.

Preserve under s. 34.

Official words: “expires at the conclusion of the 60-day period next following the occurrence of the earlier of”

Last day to file a lien: 60 days

Details · s. 31(3)(b)

Counted from: the earlier of: the person last supplied services or materials; the contract completed, abandoned or terminated; the subcontract certified complete (s. 33) (no certificate, or supply after substantial performance). Who: subcontractors, suppliers and other non-contractor claimants.

Before substantial performance, publication of the certificate is also a trigger (s. 31(3)(a)). Preserve under s. 34.

Official words: “the date on which the person last supplied services or materials to the improvement”

Court action on the lien: 90 days

Details · s. 36(2)

Counted from: the last day under s. 31 on which the lien could have been preserved. Who: lien claimants with a preserved lien.

Perfect = start an action and register a certificate of action (s. 36(3)).

Official words: “expires unless it is perfected prior to the end of the 90-day period next following the last day, under section 31, on which the lien could have been preserved”

Not for: Holdback release (annual release and payment rules in s. 26 are multi-step); contracts governed by older versions of the Act under its transition rules (not checked); workers' trust fund liens; adjudication; municipal/public-private contracts; ON is not in a reviewed ArtBuild article.