Change order dispute checklist

Find exactly what is disputed: scope, authority, quantity or price.

Version
2026.1
Last updated
October 24, 2026

Prepared by ArtBuild to help you organise your paperwork. It is general information, not legal advice, and it has not been reviewed by a lawyer. Check the rules for your province or territory before you act.

Part of the Change Orders and Extra Work Kit: start with its guide, and download the whole kit there.

Download PDF

Locate the exact disagreement

Work through one change ID at a time. A disagreement may concern scope, authority, valuation, quantity, timing or payment allocation. Separating these questions makes a factual response possible without deciding legal entitlement automatically.

Project contract change ID and revision
Dispute received date and original record
Requested approved and disputed amounts
Reviewer and next internal target
  • Identify the original contract scope and governing document version.
  • Record the proposed change and any omission or substitution.
  • Identify the instruction giver and evidence of authority.
  • Keep requests, approvals, objections and verbal confirmations in sequence.
  • Separate price approval from approval of work method or access.
  • Record completed quantity, invoice and payment status independently.

Reconcile evidence before escalation

  • Recalculate quantity times rate, overhead base, markup base and tax.
  • Check duplicate tickets, superseded estimates and labour included in subcontract charges.
  • Keep negative adjustments linked to the original item.
  • Compare schedule impact to activity dependencies and concurrent events.
  • Request specific missing documents and identify contrary evidence.
  • Check notice, invoice and dispute clauses with a qualified reviewer.
  • Preserve all originals and the exact version sent to the other party.
FindingNext operational action
Quantity differenceCompare daily records and agree or list disputed measurements.
Authority unclearRequest written confirmation of role and instruction.
Pricing basis disputedExchange a line-by-line reconciliation and assumptions.
Procedural deadline uncertainObtain prompt jurisdiction-specific review; do not invent a date.
Agreed facts and remaining issues
Proposed meeting or reconciliation
Adviser questions and source references
Owner and next action

No conclusion about payment follows solely from an unsigned form, a completed task or an unanswered email.

Before you act: this document is general information prepared by ArtBuild to help you organise facts and paperwork. It is not legal advice and has not been reviewed by a lawyer for your situation. Rules differ by province and territory and change over time. Check the official source for your project, and for deadlines, liens, court or insolvency steps, speak with a lawyer licensed where the project is located.

All Change Orders

ArtBuild template All of Canada

Change Order Register

List every change with its status, value and approval evidence.

Version 2026.1

ArtBuild template All of Canada

Change order request

Ask the client to approve a proposed change.

Version 2026.1

ArtBuild template ArtBuild resource kit · All of Canada

Change Orders and Extra Work Kit

Use this kit when you are asked to do work that is not in your contract, or when you have already done extra work and the price is disputed.

Version 2026.1

ArtBuild template All of Canada

Construction change order

Record an agreed change: scope, price, schedule and signatures.

Version 2026.1

ArtBuild template All of Canada

Extra work daily log

Record actual labour, materials and equipment each day by change number.

Version 2026.1

Protect your construction business. Create your free ArtBuild Business Hub account.

With a free ArtBuild Business Hub account you can save the documents you generate, reuse your business details on every form, and find them again later. Everything on this page stays free without an account.

Create a free account