Construction change order

Record an agreed change: scope, price, schedule and signatures.

Version
2026.1
Last updated
October 24, 2026

Prepared by ArtBuild to help you organise your paperwork. It is general information, not legal advice, and it has not been reviewed by a lawyer. Check the rules for your province or territory before you act.

Part of the Change Orders and Extra Work Kit: start with its guide, and download the whole kit there.

Download PDF Download editable Word (.docx)

Identify the revision and decision

Use this form to record an expressly agreed change. Until authorization is recorded, mark it proposed. A signature confirming attendance or daily quantities is not automatically authorization of this scope, price or schedule.

Project address and original contract date
Owner and contractor legal names
Change ID revision and issue date
Status proposed or approved
Request or instruction reference
Authorized representatives and authority basis
Original scope referenceAddition deletion or substitutionRevised scope and limits
Attachments drawings and specification revisions
Exclusions assumptions and unresolved interfaces

Record price and schedule separately

Price itemAmount CADBasis / attachment
Net direct cost[enter][labour material equipment subcontract less omissions]
Overhead[enter][rate and eligible base]
Markup[enter][rate and eligible base]
Net change before tax[enter][reconciled subtotal]
Tax and gross change[enter][tax basis and amount]
Price basis fixed unit rates or time and materials
Cap allowance or quote validity if applicable
Payment milestone invoice requirements and holdback basis
Original completion date and affected activity
Proposed calendar or working day impact and basis
Agreed revised milestone or schedule reservation

Separate anticipated duration from an agreed extension. Record overlapping delays and dependencies; do not add every activity delay to the project completion date.

Current contract value before this change excluding tax
Revised contract value after this change excluding tax

Authorization and distribution

The parties record agreement only to the described revision and completed terms. List any matter still reserved, including price components or schedule effects. Do not insert broad waivers or releases without qualified review.

Owner representative name title and authority
Owner signature and date
Contractor representative name title and authority
Contractor signature and date
Other required consultant or lender approval
Conditions that must be satisfied before starting
  • The approved revision matches the pricing attachment and scope comparison.
  • Omissions are credited once and allowances are not duplicated.
  • Tax treatment and contract total are reconciled.
  • Site supervisor has the approved scope and restrictions.
  • Copies sent to authorized parties and register updated.
Distribution list and date
Work start instruction and limits
Internal review and unresolved legal questions

This draft does not determine the effect of an unsigned change or override the governing contract or consumer legislation.

Before you act: this document is general information prepared by ArtBuild to help you organise facts and paperwork. It is not legal advice and has not been reviewed by a lawyer for your situation. Rules differ by province and territory and change over time. Check the official source for your project, and for deadlines, liens, court or insolvency steps, speak with a lawyer licensed where the project is located.

All Change Orders

ArtBuild template ArtBuild checklist · All of Canada

Change order dispute checklist

Find exactly what is disputed: scope, authority, quantity or price.

Version 2026.1

ArtBuild template All of Canada

Change Order Register

List every change with its status, value and approval evidence.

Version 2026.1

ArtBuild template All of Canada

Change order request

Ask the client to approve a proposed change.

Version 2026.1

ArtBuild template ArtBuild resource kit · All of Canada

Change Orders and Extra Work Kit

Use this kit when you are asked to do work that is not in your contract, or when you have already done extra work and the price is disputed.

Version 2026.1

ArtBuild template All of Canada

Extra work daily log

Record actual labour, materials and equipment each day by change number.

Version 2026.1

Protect your construction business. Create your free ArtBuild Business Hub account.

With a free ArtBuild Business Hub account you can save the documents you generate, reuse your business details on every form, and find them again later. Everything on this page stays free without an account.

Create a free account