ArtBuild template ArtBuild template · All of Canada
Change order request
Ask the client to approve a proposed change.
- Version
- 2026.1
- Last updated
- October 24, 2026
Prepared by ArtBuild to help you organise your paperwork. It is general information, not legal advice, and it has not been reviewed by a lawyer. Check the rules for your province or territory before you act.
Part of the Change Orders and Extra Work Kit: start with its guide, and download the whole kit there.
Download editable Word (.docx)
Request a documented decision
Use this request before treating a proposed change as approved. Attach enough detail for the authorized recipient to accept, reject or ask questions about the specific revision. Complete optional fields only where relevant.
- Project contract and change ID
- Request revision and date
- Requester and recipient with roles
- Reason client selection concealed condition or other
- Original drawing clause or quantity
- Proposed scope and exclusions
| Item | Original requirement | Requested change | Evidence / drawing |
|---|
- Proposed price before tax and calculation reference
- Tax basis and gross requested amount
State consequences and obtain the response
- Affected activity and current milestone
- Estimated duration and schedule assumptions
- Materials lead time and decision needed by
- Optional alternatives and respective costs
- Work status not started underway or complete
- Authority for any work already performed
Suggested request: Please review change [ID/revision] for [scope]. The attached price is [basis] and the schedule effect is [proposal or unresolved]. Please confirm your decision and authority in writing. The requested decision date [date] is an administrative planning target. We have not treated this request as approval.
| Recipient decision | Details / conditions | Name capacity and date |
|---|---|---|
| Approved revision | [enter] | [enter] |
| Rejected or revised request | [enter] | [enter] |
| Further information needed | [enter] | [enter] |
- Response received and evidence location
- Next owner action and target
- Approved change-order reference if issued
Do not infer acceptance from silence. Record any contractual or legal notice question for qualified review before relying on a deadline or changing performance.
Before you act: this document is general information prepared by ArtBuild to help you organise facts and paperwork. It is not legal advice and has not been reviewed by a lawyer for your situation. Rules differ by province and territory and change over time. Check the official source for your project, and for deadlines, liens, court or insolvency steps, speak with a lawyer licensed where the project is located.